The problem
A sprinkler head was struck and discharged during forklift operations, releasing water across the warehouse floor and into an adjoining office area before the system could be isolated.
The tenant needed the warehouse floor operational within days to avoid disrupting shipping commitments.
What we found
The warehouse floor itself dried quickly, but the office area's drywall and carpet required removal, and stored inventory near the discharge point had water damage.
Ceiling tiles above the office had absorbed enough water to require replacement to prevent sagging.
The solution
We prioritized extraction and drying in the warehouse to restore operations within 48 hours, then completed drywall, ceiling tile, and flooring reconstruction in the office area on a separate timeline that didn't affect shipping.
Result
Warehouse operations resumed within two days. The office reconstruction was completed within the five-week total project window with full insurance documentation.