Tenant improvement drywall and finishing
A new office tenant required partition walls and a Level 5 finish to meet their design specification before move-in.
- Location
- Vancouver, BC
- Building
- Commercial office suite
- Service
- Drywall
- Scope
- New partition walls, taping, and Level 5 finish, 600 m² office suite
- Duration
- 4 weeks
- Completed
- 2025
The problem
A new tenant leasing a 600 m² office suite needed new partition walls built to their layout plan, with a Level 5 finish specified for areas with critical lighting and gloss paint.
The build-out needed to be complete before the tenant's move-in date, which was fixed by their existing lease expiry.
What we found
The design called for several curved partition sections and sound-rated walls around meeting rooms, requiring careful framing coordination before drywall installation.
Critical lighting in the reception area would show any imperfections in a standard finish, requiring the full Level 5 skim coat.
The solution
We installed the specified partition framing and sound-rated assemblies, hung and taped drywall to the design layout, and applied a full Level 5 skim coat in the reception and meeting room areas before priming for paint.
Result
The build-out was completed on schedule for the tenant's move-in date, with a flawless finish under the reception area's critical lighting.