Common area drywall repair after flood
A burst pipe in a mechanical room damaged corridor and lobby drywall requiring fire-rated assembly reinstatement.
- Location
- West Vancouver, BC
- Building
- Multi-family strata building
- Service
- Drywall
- Scope
- Corridor and lobby drywall replacement, fire-rated assembly reinstatement
- Duration
- 3 weeks
- Completed
- 2024
The problem
A burst pipe in a second-floor mechanical room flooded an adjacent corridor and part of the lobby, damaging drywall that was part of a fire-rated corridor assembly.
The strata needed the fire-rated assembly properly reinstated, not just cosmetically patched, to maintain code compliance.
What we found
The damaged drywall was part of a two-layer fire-rated assembly, and one full layer needed replacement to maintain the rating.
Water had also affected an adjacent electrical panel enclosure requiring an electrician to confirm safety before work proceeded.
The solution
We removed and replaced the damaged fire-rated drywall layers per the original assembly specification, coordinated electrical sign-off before enclosing the panel area, and matched paint and finish to the existing corridor.
Result
The corridor and lobby were restored to their original fire-rated specification with documentation provided to the strata for their records.
"They knew the fire-rating requirements without us having to explain it. That mattered for our records."
Before & after